Martinsbrugg
Regloplas AG

REGLOPLAS New company headquarters in Martinsbrugg
Six floors each with 2,500 m² of floor space
Building owner partnership

Investment in the future


REGLOPLAS, a leading manufacturer of temperature control units for the processing industry, can look back on a positive balance sheet in recent years. The demand for products has steadily increased. In order to be able to keep up on the world market in the future, the company headquarters are being expanded. The new building in Martinsbrugg will be built over six floors on a floor space of 2,500 m² per floor. The project scores with a sustainable planning concept and an environmentally friendly design of processes. The plan is to use the entire roof area for photovoltaics in order to cover the highest possible proportion of process energy consumption from in-house production.

The new building impresses with a modern and openly designed working environment. Digitalized processes enable efficient procedures and support the goal of establishing the REGLOPLAS new building as a smart factory.

To display the map from Google Maps, the script must be allowed to load.
  • Attractive commercial and industrial area in the east of the city of St. Gallen
  • Close to the freeway, good connection to public transport
  • Numerous restaurants and shopping opportunities

construction progress

We would be happy to keep you up to date!

April 2022

The building shell including all rough-in installations has been completed. The final fit-out with heating, cooling, ventilation and sanitary work will now follow. The high-bay warehouse is about to be put into operation, and the automated pallet lift is also currently in the final assembly stage. Furthermore, work is currently being carried out on the roof to place the photovoltaic system at its destination shortly.

At the end of April, the cleaning work on the facade and windows will be finalized, after which the facade scaffolding can be removed.

January 2022

The completion of the building envelope (roof and facade) is currently in progress. At the same time, the building technology is in the basic assembly and distribution phase. Metal construction work such as fire protection glazing to the inner courtyard is in the completion phase and the elevators are all being installed.

September 2020

The lines for the geothermal probes have been laid – 25 x 250 m = 6.25 km

September 2020

25 geothermal probes were drilled to a depth of 250 meters for heating and cooling.

September 2020

In addition to the excavation, work is now also being carried out on securing the excavation pit.

August 2020

The building site is being prepared and the excavation is in progress.