Living Andrius
December 2025

House A: The reinforcement coating on the composite thermal insulation system has been completed and the final coating will be applied in early 2026. The rough installations have been completed, all screeds have been laid in the building, and interior plastering work is currently underway.

House B: The preparatory plumbing work on the roof has been completed and the roof tiles are now being laid. The composite thermal insulation system has been installed and the reinforcement layer is now being added. The rough installations have been completed on the ground floor and first floor, the foam concrete has been poured, and the underfloor heating is currently being laid. The screed is scheduled to be poured at the end of this week. On the second floor and top , the internal partition walls top built and the rough installations are currently underway.